We are relieved to announce that the mitigation construction is at the finishing line as the berm on Range 3 now has the height required by the CFO inspection report from the previous summer. While improvements to the rest of the range had been complete during the COVID layoff, we had to wait for sufficient material to be available and a stretch of dry weather to permit crews to do their work on Range 3. Now with rains expected soon, the berm will be hydroseeded to retain its shape. The raised berm permits shooting from distance again.
In addition an excavator repaired the bottom of the berm on Range 10.
A work party will be announced so that the ground baffles can be placed in their designed configuration, filled and capped. With that, our mandated work will be completed. We will mark that moment with a socially distanced ceremony with our thanks to all the volunteers, staff and contractors who made this happen.